Completion Certificate
United Business Park (UBP) SEZ
UBP SEZ provides a structured process for issuing a Completion Certificate to ensure that industrial units comply with all regulatory, safety, and operational standards.
Application Requirements
Applicants can apply for a Completion Certificate after the factory has been operational for at least three (03) months. The application must include:
- Three (03) sets of as-built drawings (Ammonia Prints) signed by the owner and architect
- Soft copy of as-built drawings (CD or digital format)
- Environmental Clearance Certificate from the relevant authority
- Firefighting system plan along with compliance certificate
- Social Security Registration Certificate
- EOBI Registration Certificate
- Insurance Registration Certificate
- Labour Welfare Registration Certificate
- Electrical Industrial Design (signed and stamped by a PEC-registered engineer — Pakistan Engineering Council)
- Structural Stability Certificate (as per applicable by-laws)
Inspection & Evaluation
- The submitted case will be reviewed by the concerned department.
- A physical inspection of the factory will be conducted to verify compliance with approved plans and safety standards.
Approval Process
- After successful inspection, the case will be forwarded for approval by the competent authority.
- Upon approval, the process for issuance of the Completion Certificate will be finalized.
Issuance
- The Completion Certificate will be formally issued after final approval by the relevant authority.